Terminal improvement completes
Construction of the Barbours Cut Terminal Container Yard 3N for the Port Houston Authority has completed.
The project is part of a modernisation plan to improve cargo handling and adds around 40,500 square metres of new container storage at the terminal.
The work was carried out be McCarthy Building Companies and included utility upgrades, new high-mast light poles and a realignment of the main interterminal access road. Work began in June 2021 and was substantially completed two months ahead of schedule.
“McCarthy has been working with the Port Houston Authority for more than 25 years, and we were honoured to once again work together as they move to modernise the port to meet growing demand,” said Fitz O’Donnell, vice president marine/industrial for McCarthy Southern Region.
“McCarthy has a wealth of experience in both over-water and land-side port work, and our ability to self-perform work allows us to provide top-level results for our clients.”
The container yard required 39,000 square metres of pavement demolition and involved bringing in 18,000 cubic metres of concrete pavement and 24,500 cubic metres of base and subbase materials.
Over 1,500 metres of utilities were installed, including 550 metres of ductile iron water lines, 550 metres of precast trench drains, 290 metres of cast-in-place electrical duct banks, and 137 metres of pressurised sanitary sewer lines.