APM Terminals advances Rotterdam expansion plans

APM Terminals and Rotterdam port authority are advancing plans for a 1.4 million teu capacity expansion

APMT Maasvlakte II aerial shot
APM Terminals and Rotterdam port authority are advancing plans for a 1.4 million teu capacity expansion Source: Danny Cornelissen

APM Terminals Maasvlakte II and the Port of Rotterdam Authority are progressing plans for the next phase of expansion at the Dutch container terminal, adding 25 hectares of operational space and approximately 1.4 million teu of annual handling capacity.

The development will include an additional 711 metres of quay, extended crane infrastructure and supporting maritime facilities, strengthening the Port of Rotterdam’s ability to accommodate future growth in container shipping.

Harold Kunst, managing director of APM Terminals Maasvlakte II, said: “This expansion marks the next step in the long-term development of our terminal. We are creating space for future growth while continuing to develop a terminal that can serve our customers safely, reliably and efficiently over the long term.”

The expansion is being delivered in phases, allowing the existing terminal to remain fully operational. The first part of the development has recently entered operation, with preparations now moving forward for the next stage.

Under the partnership, APM Terminals will oversee the development of terminal operations, while the Port of Rotterdam Authority will deliver the necessary maritime infrastructure. This includes extending the existing quay wall by 711 metres, extending the landside crane rail by 428 metres and dredging approximately 1.3 million cubic metres of sand.

The additional infrastructure will accommodate deepsea, feeder and inland shipping vessels. The project supports the shared ambition to strengthen Maasvlakte II’s position as one of Europe’s leading container hubs.

Boudewijn Siemons, chief executive of the Port of Rotterdam Authority, said the investment would strengthen logistics chain resilience, security of supply and the competitiveness of the Dutch economy.

APM Terminals Maasvlakte II has invested in its facilities at Prinses Amaliahaven since 2008. The fully automated terminal uses electrified equipment, automated guided vehicles and remotely operated quay cranes.

Technical planning, scheduling and procurement preparations will continue in the coming months. The Port of Rotterdam Authority’s shareholders are expected to make an investment decision in February 2027.

Pre-selection is scheduled for publication on TenderNed in January 2027, with the quay wall tender award phase expected to begin in March. Construction is planned to run from October 2027 until January 2030.